water capacity by 40,000 tons without
using power from the local grid.
The TECO CHP system will reduce
local emissions of carbon dioxide by
82,907 metric tons of carbon equivalent
per year – equal to removing the carbon
that would be absorbed by 82,907 acres
of forest or removing the carbon emissions
of 51,817 cars. The CHP system is designed
to meet all the requirements of the Texas
Commission on Environmental Quality,
which regulates the enforcement of local
air-quality standards.
TECO’s master plan also called for
significant growth of the company’s
chilled-water operations. This was in
response to the plans projections that
the Texas Medical Center’s chilled-water
load would increase by 30,400 tons over
the next five years; 38,300 tons over the
next six to 10 years; and 12,400 tons over
the next 11 to 15 years.
Implementation Launched
Once TECO’s master plan and its
recommendations were complete, TECO
then contracted with Burns & McDonnell
to review the plan and provide input
from an implementation perspective.
During this review period TECO decided
to make the following revisions to the
master plan:
Install two 45 MW CHP units, one in
future, instead of three 30 MW units
Install one chilled-water storage tank,
vs. two, on the central plant site, and
install the second future tank off site
In July 2007, TECO received final
board approval adopting the master plan
and funding to proceed with the initial
implementation projects totaling $367
million. The five-year implementation
phase was then launched. TECO selected
Jacobs Carter Burgess as the owner’s
engineer for design build contracts and
engineer of record for design/bid contracts.
Burns & McDonnell was selected as the
design/build firm.
The new thermal storage system,
which will enhance chilled-water pro-duction economics, is already under
construction and is scheduled to come
online in June 2009. The new chiller
facility, designed to hold ten 80,000-ton
chillers, will be constructed on the former
site of the Texas Medical Center Hospital
Laundry Cooperative Association building, which was demolished in 2007. The
first 32,000 tons of the new facility’s
capacity are projected to be operational
in early 2011.
The initial phase also will include
expansion of the distribution system
including installation of a 42-inch
chilled-water loop on the west side and
a 60-inch water loop to the south, with
all distribution-related work totaling
approximately $50 million.
The full implementation of TECO’s
master plan will result in a total of 90-
100 MW of gas turbine power generation; 3-6 MW of back-pressure steam
turbine power generation; 80,000 tons
of chilled-water generation; additional
steam capacity; and 150,000 ton-hr of
thermal energy storage. The master plan
provides emergency chilled-water generation capacity for 60 percent of TECO’s
peak load.
The mission of TECO is to provide
economical and reliable thermal services
to highly critical institutions in the Texas
Medical Center. Supported by the expertise
of Jacobs Carter Burgess, TECO will be
able to expand as needed to keep pace
with the service needs of the medical
center institutions and to operate one of
the largest and most up-to-date thermal
systems in the world. More important,
TECO will be saving its customers money,
at a time when cost containment is imperative in the healthcare field.
Stephen K. Swinson, PE, is
president and chief executive officer
of Thermal Energy Corp. Swinson
has more than 20 years’ experience
in the district energy industry,
including positions at Trigen Energy
Corp. and Auburn University. He served as IDEA’s
chair from 1996 to 1998. A licensed professional
engineer, Swinson is a graduate of Auburn
University with a bachelor of science degree in
mechanical engineering, Northwestern University’s
Kellogg Graduate School of Management with
an MBA. He may be reached at sswinson@
teco.tmc.edu.
William Lynn Crawford, PE,
is a program manager for Jacobs
with more than 35 years of experience as a facility manager, a
design/build contractor and a consulting engineer. He is a graduate
of The University of Houston with a bachelor of
science degree in mechanical engineering and
is a licensed professional engineer. Crawford
specializes in large energy projects. He may be
reached at lynn.crawford@jacobs.com.
STAY IN IT
FOR THE
LONGER RUN.
Upgrade and Revamp.
Changes in your operating
requirements don”t always mean
new equipment. Dresser-Rand
offers a broad range of upgrades
to maximize reliability and extend
mean time between repairs. We also
provide a number of comprehensive
revamp solutions to help meet your
changing performance requirements.
So, regardless of who originally
manufactured the equipment,
wehavetheproductdesignsand
experienced technical resources to
help keep your rotating equipment
on track—and your business up
and running.
Dresser-Rand is the winner
of Frost & Sullivan’s 2008
North American Compressed
Gas Solutions Company of
the Year Award.
The Americas: (Int”l + 1) 713-354-6100
ESA: (Int”l + 33) 2-35-25-5225
Asia-Pacific: (Int”l+ 60) 3-2093-6633
info@dresser-rand.com