Figure 2. Monthly Production of Electricity and Chilled Water at Kuala Lumpur
International Airport Plant, 2007.
30
25 RTh kWh
Source: Adapted from GDC (Holdings) Sdn. Bhd.
20
Millions
15
10
5
0
Jan Feb Mar Apr May
Two 12-ton/hr heat recovery steam
generators
One 6-ton/hr steam auxiliary gas
boiler
Two 4. 2 MW gas turbine generators
Note that, at present, there are no regulations on gas sulfur emissions in Malaysia.
Currently, the gas district cooling plants
are considered Independent Power
Producers and are regulated by the
Energy Commission of Malaysia.
For all five of these cogenerated gas
district cooling plants, GDCSB was the
main plant developer and initial operations
and maintenance company. However, plant
ownership, operating parameters and
tariff rates vary from system to system
(see table 1).
Jun Jul Aug Sep Oct Nov Dec
2007
Plant Development
and Operations
The Kuala Lumpur City Centre plant
was developed to supply the chilled-water requirements of the various city
center customers. The center’s commercial
buildings, including hotels, were planned
and developed at the same time as the
gas district cooling plant. In total, the
complex covers an estimated of 604,000 sq
m ( 6. 5 million sq ft) of space consisting
of offices, a retail center, hotel and a
mosque. The Kuala Lumpur City Centre
plant started operation in 1997.
The Kuala Lumpur International
Airport plant, which started operation
in 1998, supplies electricity and chilled
water to the main terminal building, the
administrative building, contact pier, air-traffic control tower, satellite building,
engineering and customs complex and
other privatized facilities at the airport
with a total floor area of 605,320 sq m
( 6. 52 million sq ft). The plant’s average
monthly electricity and chilled-water
production is shown in figure 2. Last
year, the monthly demand for electricity
varied from a minimum of 12. 35 x 103
MWh for June to a maximum of 25. 27 x
103 MWh for March. Chilled-water pro-duction varied from 8.01 million tons
during September to 10. 21 million tons
during May.
While both the city center and airport
plants were built to serve the commercial
sector, the Putrajaya cogenerated gas
district cooling plants serve slightly different objectives. Putrajaya is a new
mixed development, consisting mainly
of federal government ministry offices
as well as residential and shopping
complexes. Putrajaya is considered a
showpiece of the federal government,
with buildings designed and constructed to incorporate the most modern facilities and infrastructure. Those buildings
include the prime minister’s secretariat,
the Malaysian king’s palace, federal ministries offices, the national convention
center, central mosque, five-star hotels,
Table 1. Ownership and Operation of Malaysia’s Gas District Cooling/Cogeneration Plants.
Plant
(Start Date)
Users
Owners
Supply/Return
Chilled-Water
Temperatures
Degrees C (F)
Maximum
Demand Charge
Malaysian
Ringgits/kW/month*
(U.S. $)
Tariff
Charge
Malaysian
Ringgits/kW/month*
(U.S. $)
Kuala Lumpur
City Centre
(1997)
Offices,
shopping mall,
hotels
KLCC
Properties
Holdings
4. 4 /14.4
( 39.9/57.9)
19. 50
( 6.0)
Tariff: C1
Peak: 0.2340 (0.07)
Off Peak: 0.2340 (0.07)
Kuala Lumpur
International Airport
(1998)
Airport
complex
Malaysia
Airport Berhad
7.5/14.5
( 45.5/58.1)
23. 40
( 7. 20)
Tariff: E3
Peak: 0.222 (0.068)
Off Peak: 0.133 (0.041)
Putrajaya
Plant 1 (1998)
Plant 2 (1998)
Government
offices
Putrajaya Holdings
GDC Putrajaya Sdn. Bhd.
7.5/14.5
( 45.5/58.1)
29.00
( 8.90)
Tariff: C1
Peak: 0.238 (0.073)
Off Peak: 0.128 (0.039)
University
Technology Petronas
(2001)
Academic
buildings,
mosque,
auditorium,
library and
offfices
Institute
Technology
Petronas
Sdn. Bhd.
6/13
( 42.8/55.4)
17. 30
( 5. 30)
Tariff : C1
Peak: 0.165 (0.051)
Off Peak: 0.11 (0.034)
* Tariff imposed by Tenaga Nasional Bhd., the main utility company in Malaysia. The tariff was to be revised in July 2008.
Source: University Technology Petronas, adapted from GDC (Holdings) Sdn. Bhd. and Tenaga Nasional Bhd.