development of the construction documents and basis of design criteria, through
construction, startup, commissioning,
and environmental and operational performance testing.
Optimum Efficiency +
Environmental Performance
When the new $120 million central
heating plant begins full operation in
spring, it will produce nearly twice as
much steam energy and five times more
electric power than the existing plant.
However, its principal advantage as a
district steam plant using advanced CHP
technologies is that with all this power
being generated, it will actually produce
seven times less greenhouse gas emissions,
on a tons-per-year basis, than the older
central heating plant. By using treated
Act did not require either a public hearing
for the facility or the filing of an environmental impact report.
The CHP plant will achieve optimum
energy efficiency with a combined 10 MW
combustion turbine, 6. 5 MW of high- and
low-pressure steam turbines, a heat recovery steam generator and three package
boilers – each rated for 131,000 lb/hr of
steam (fig. 2). Four package boilers had
originally been planned. However, after
the university invested $43 million in
energy performance improvements
throughout campus, reducing steam and
electric demand by an average of 20 percent, the CHP plant was downsized during
design by one package boiler.
The signature building housing the
energy facility anchors the northwest
corner of campus and is sited next to
the Mullins Center, a sports arena, and
faces the main athletic fields. A ‘big roof’
concept covers both the 45,000-sq-ft
energy building and a 40,000-sq-ft tank
farm area, with the entire complex ‘reading’
architecturally as one building complex.
Comprehensive air permit applications
filed with the Massachusetts Department
of Environmental Protection (MA DEP)
included air quality and noise impact
assessments and control technology evaluations. The boilers are permitted on the
basis of large industrial boilers, limiting
particulate emissions (PM10) to 0.02 lb/
MMBtu on gas and 0.04 lb/MMBtu on oil.
For NOx, the permit levels were 5.0 ppmvd
on natural gas and 9.0 ppmvd on oil for
the package boilers. Similarly, the NOx
permit level was 6.0 ppmvd for the com-
TURN TO
A LEADER.
The new central heating plant
will produce nearly twice as much
steam and five times more power
than the existing plant – and
seven times less greenhouse
gas emissions.
wastewater effluent, reducing groundwater
demand and emitting fewer pollutants
than current operations, the new CHP
system will actually cause improvements
to local environmental conditions. To this
point, the state enforcement agency for
the Massachusetts Environmental Policy
Figure 2. UMass Amherst Central Heating Plant Steam Flow Diagram.
Steam Turbine Generators.
For your next steam turbine generator,
turn to Dresser-Rand, a leader in rotating
equipment with approximately 62,000
steam turbine installations in 140+
countries. For more than a century, our
rugged turbine generator sets have been
reliable sources of on-site power and
distributed energy from . 5 to 100 MW
for many industries and applications:
Oil and gas
Pulp and paper
Ethanol
Palm oil
Process industries
Universities
Municipalities
So when you’re ready to select
a steam turbine generator from a
manufacturer with unsurpassed
experience in rotating equipment,
turn to Dresser-Rand.
HRSG
HP
BLR
10 MW G1
600 PSIG HEADER
The Americas (713) 467-2221
European Served Areas 33-2-35-25-5225
Asia Pacific 603-2093-6633
info@dresser-rand.com
TO CAMPUS
DISTRIBUTION
BUILDING
HP STEAM
TURBINE
2 MW
PRV/DESUPERHEATER
200 PSIG HEADER
Source: University of Massachusetts Amherst.
www.dresser-rand.com
TO CAMPUS
DISTRIBUTION
BUILDING
LP STEAM
TURBINE
4 MW
PRV/DESUPERHEATER
20 PSIG HEADER
LP
BLR
LP
BLR
LP
BLR