recovery steam generator is the lowest
rate for an industrial boiler and combustion turbine generator approved for BACT
standards in the country, as determined
by the U.S. Environmental Protection
Agency’s RACT/BACT/LAER Clearinghouse
( http://cfpub1.epa.gov/rblc/htm/bl02.cfm).
The CHP operation uses an advanced
10 MW dual-fuel combustion turbine in
combination with a highly efficient combined-cycle system of heat recovery and
steam turbine-driven electric generation
to achieve a nearly ideal heat rate. All of
this is housed in an architecturally unique
and attractive building that befits the
campus’s setting (fig. 1).
Planning Commences
To pay for the project, the campus
sought a tax-exempt bond issue in 1999,
financed by the University of Massachusetts
Building Authority and funded through
student activity fees. As the Building
Authority is a separate state agency from
the UMass system, this required close
coordination and cooperation between
the two agencies. The Building Authority,
through its executive director, David
MacKenzie, is responsible for capital
financing, design and construction of the
CHP system, while the UMass campus is
responsible for CHP staffing, operations
and maintenance.
Conceptual planning began when
UMass retained Levitan & Associates of
Boston in 2000 to evaluate the size and
cogeneration options for a central heating
plant at the UMass Amherst campus;
Sebesta Blomberg further advanced the
project in 2002. Through these firms’
insightful technical and economic analyses,
the campus became convinced that a
cogeneration facility sized for its specific
steam and electric loads was as economical on a cost-per-kilowatt or pound-of-steam basis as a larger facility designed
to export power off campus.
The CHP plant is designed to meet
the campus steam and electric demands
for the next 20 years, providing 16 MW
and up to 360,000 lb/hr of steam, with
one boiler in spinning reserve. Systems
controls allow the facility to follow the
campus steam demand while generating
electric power to meet most of the campus electric demand. The campus will
continue to import some electric power
during peak demand periods.
Striking a balance between the economies of a smaller cogeneration facility
sized for campus-only loads versus a
larger energy facility designed to export
power, the UMass CHP concept was born.
As the facility was financed with tax-exempt
bonds, it is designed to meet only campus
loads ‘inside the fence,’ and not to wheel
and sell power off site.
Sebesta Blomberg supported negotiations with the local natural gas distribution company, Berkshire Gas Co. The
resulting gas delivery project was designed,
permitted and constructed by Berkshire
Gas, which completed its work ahead of
schedule to support first fire in the combustion gas turbine in December 2007.
Startup and commissioning of the three
package boilers is set for January 2008.
The physical plant also retained
R.W. Beck of Boston in 2005 to assist in
the development of staffing plans, an
operations budget and a 10-year preventive maintenance plan for the new CHP
plant. Boston-based Vanderweil Engineers
and an experienced team of consultants,
including Cambridge Seven Architects,
were selected by the UMass Building
Authority to permit and design the project.
“The last four years have been intense,”
notes Physical Plant Director Pat Daly. The
Vanderweil project team assisted the
Building Authority and UMass Amherst
beginning in 2002 with a rigorous site
selection process, demand forecasts and
economic pro formas for sizing and
designing the CHP installation. As the
project team completed engineering
studies in 2003, and began detailed CHP
designs in 2004, it also applied for comprehensive air and environmental permits
to various state and federal agencies.
To preload the building site, the project team designed and monitored the
import of 160,000 tons of gravel two years
before building construction. Preloading
caused soft, varved clays underlying the
site to settle two feet, avoiding the more
expensive option of pile foundations. The
campus also completed an early steam
tunnel construction package, built by Daniel
O’Connell’s Sons of Holyoke in 2005, and
began negotiations of an electric interconnection agreement with Western Massachusetts Electric Co. in 2006.
Completing hundreds of construc-
Courtesy University of Massachusetts Amherst.
The boiler hall within UMass Amherst’s new
central heating plant.
tion documents and thousands of pages
of specifications, the CHP design team
integrated 19 complex, engineered plant
systems into a handsome building design.
The project was publicly bid in September
2005, and a construction manager contract
was awarded to O&G Industries of Tor-rington, Conn., that winter.
Construction on site began in January
2006. The project is entering its startup
and commissioning phase this fall, with
completion and handoff to UMass Physical
Plant scheduled for March 1, 2008.
UMass Amherst, the Building Authority
and Vanderweil’s project management
team created an independent engineer/
commissioning agent process and request
for proposals for the new CHP system –
one of the first times this process has
been used in the industry. By selecting
the team of Sebesta Blomberg and Penn
Power, UMass integrated a total quality
assurance framework throughout the
CHP project using commissioning as its
foundation.
“This quality framework, layered over
project design and construction processes
and procedures, includes both peer review
and facility commissioning plans and
specifications,” explains Daly. “We think
it will result in a smooth turnover from
the Building Authority to the campus with
very reliable operation.”
The CHP commissioning program
ensures that the original design intent for
the new CHP plant will be met – from