capacity from 3,500 to 60,000 ton-hours;
● the median TES capacity per installation
is 16,000 ton-hours;
● the average TES capacity per installation
is 19,431 ton-hours;
● the average peak cooling-load shift per
installation is 2,776 tons;
● the average peak electric-demand
reduction per installation is 2. 1 MW;
● the total peak cooling-load shift is
nearly 203,000 tons; and
● the total peak electric-demand reduction is more than 152 MW.
Latent-heat TES, in which cooling is
stored as the phase change of a storage
medium (generally as ice), represents
nearly 400,000 ton-hours ( 22 percent) of
TES capacity installed on campus. Of the
installations using this technology,
● 86 individual installations range in TES
capacity from 320 to 93,200 ton-hours;
● the median TES capacity per installation
is 2,350 ton-hours;
● the average TES capacity per installation
is 4,526 ton-hours;
● the average peak cooling-load shift per
A Note on
Survey Methodology
Courtesy of Chicago Bridge & Iron Co.
This 30,000-ton-hour stratified chilled-water TES installation at the University of Texas in El Paso began
operation in 1999. It was designed to complement the architectural style prevalent on campus. Such installations are often sited remotely from the main campus chiller plants, allowing the TES to function as a
satellite chiller plant during on-peak discharge periods. In this manner, TES can act not only to peak-shave
electric power demand but also to enhance campus distribution network capacity.
Campus Sensible-Heat TES by TES Storage Medium
Type of TES TES Storage Total Campus TES Installations by TES Supplier
Technology Medium No. Avg. (ton-hr) Total (ton-hr) (% of total)
Sensible-Heat TES CHW 71 19,230 1,365,312 96%
Sensible-Heat TES CHW (LTF*) 4 40,300 161,200 11%
Sensible-HeatTES LTF 1 40,000 40,000 3%
Sensible-HeatTES HW 1 13,167 13,167 1%
All Sensible- all media 73 19,431 1,418,479 100%
Heat TES
Initially operating as CHW TES, but also designed for potential future expansion as LTF TES.
Although some of the system data in
this survey was obtained directly from
the owners and operators, most of the
information was compiled by the author
over a number of years and then recently
expanded and confirmed through a survey
of all the leading suppliers of latent-heat
(ice) TES and sensible-heat (chilled-water
or low-temperature fluid) TES systems.
The author notes the following caveats
regarding the data:
1. The survey was conducted only through
September 2004.
2. The survey was limited to college and
university campuses, plus a few national
(U.S. and non-U.S.) research laboratory
campuses. At this time, other campus
applications are not included, such as
grade K- 12 educational facilities, medical
complexes (other than those on university
campuses), museums, airports, and military,
administrative and other government
campuses. The database also does not
include campuses that purchase chilled
water from district energy utilities that
may themselves employ TES.
3. Data from all leading TES equipment
suppliers was included. For those who
did not respond to the survey directly, a
detailed review of their published literature was done to collect data.
4. Though it does not identify 100 percent of campus TES systems, the database includes the vast majority (perhaps
90 percent or more) of U.S. TES installations and a lesser number of non-U.S.
installations.
5. Quantitative data on individual installations are sometimes approximate, due to
the necessary use of estimates in a few
instances. In those very few instances
where no quantitative individual data was
available, the average value from similar
installations was assumed. Cumulative
data (e.g., totals, averages and means)
are judged to be relatively accurate.
6. On average, peak thermal-load shifts
(in tons) are estimated to be the ton-hour
capacity divided by seven hours. On average, peak electric-load shifts are calculated at the rate of 0.75 k W/ton (including
chillers, condenser water pumps and
cooling tower fans).
7. Abbreviations: “CHW” = Chilled
Water, “LTF” = Low-Temperature Fluid.